Deconstruction of Copco No. 1 Underway

Work progresses on the second of four dams slated for removal on the Klamath River.

Following last Friday’s successful test blast, the Klamath River Renewal Corporation will proceed with the removal of the Copco No. 1 Dam, the second dam to be removed as a part of the Klamath dam removal project. The Copco No. 1 Dam, constructed in 1918 for the sole purpose of hydroelectric power generation, has blocked fish passage for over 100 years and is expected to be fully removed by the end of August 2024.

 “We are excited to get to work,” said Mark Bransom, CEO of the Renewal Corporation. “With the initial phase of drawdown complete, the dam is fully exposed and can safely be disassembled.”

 Copco No. 2, a diversion dam that was located just downstream of Copco No. 1, was removed last year. The remaining three dams, Copco No. 1, Iron Gate, and JC Boyle created reservoirs that needed to be drawn down before removal could begin. The initial phase of drawdown concluded last month, and shortly thereafter FERC approved an advancement in the schedule, allowing for the removal of Copco No. 1 ahead of the other remaining dams.

Iron Gate and JC Boyle, which are clay core earthen dams, will remain at their full height until the spring runoff period has concluded and the Klamath River has returned to baseline flows. Work on their deconstruction will likely begin sometime in May, depending on precipitation.

Deconstruction of the Copco No.1 Dam, which will be performed through a repetitive cycle of drilling, blasting, and chipping, can begin before the spring runoff period has concluded because it is a concrete arch dam. So, should the Klamath River experience a significant flow event this spring, water could safely pass over the partially removed concrete dam and the dam would remain securely in place. The Copco No. 1 Dam removal plan was specifically designed to allow for this safe flow passing, should it occur.  

The removal of Copco No. 1, Iron Gate, and JC Boyle Dams is expected to be complete sometime this fall, in time for the Fall run of Chinook salmon. The restoration of the former reservoir footprints is currently underway and will continue for several years until vegetation is successfully established and water clarity has returned to baseline conditions.

Previous Article

City election close, not decided

Next Article

Get involved in the Modoc Fair event

You might be interested in …

Swinerton Mountain View Project Prefab Walls

Progress continues to be made on Modoc Medical Center’s Mountain View Skilled Nursing Facility and hospital addition. This project marks Swinerton Builders’ second venture with MMC, equipping the team with invaluable experience dealing with Modoc’s […]

Modoc County Road Commission

On April 26, 2024, there was a break in to the Active Construction Site at the Veteran’s Memorial and Dorris Park. Moving forward if anyone is caught or suspected of entering the site without authorization, […]

Modoc County Sheriff’s Blotter

Modoc County Jail As of Monday, there are 29 people in the Modoc County Jail, 3 females and 26 males. Jail capacity is 43. There is 1 additional incarcerated person currently serving time in another […]

Modoc 4-H Shooting Sports Team

The Modoc 4H “Dirt Squirrels” Shooting Sports team competed in our Annual Top Shot Competition on Sunday April 14th. We had 22 members compete, disciplines offered were Rifle, Shotgun, Pistol, Muzzleloader and Archery. Our Top […]